China Railway 25th Bureau Guangzhou Zhuhai railway 1st bid spring "Gongshi" acceleration

China Railway 25th Bureau Guangzhou Zhuhai railway 1st bid spring "Gongshi" acceleration

China Construction machinery information

Guide: in the dispatching office of the project headquarters (hereinafter referred to as the project department) of Guangzhou Zhuhai railway SG-1 bid 2 company of China Railway 25th bureau group, there is a progress wall: there are nearly 70 pages of A4 paper on the wall, with four boxes arranged horizontally on each page, Eight or ten circles are vertically arranged in each box; A box represents a

there is a "progress wall" in the dispatching office of the project headquarters (hereinafter referred to as "project department") of Guangzhou Zhuhai railway SG-1 Lot 2 company of China Railway 25th Bureau Group: there are nearly 70 pages of A4 paper pasted on the wall, four boxes are arranged horizontally on each page, and eight or ten circles are arranged vertically in each box; A box represents a pier location and a circle represents a pile hole. Every time a pile hole is poured, the dispatcher Xiao Zhong will gently paint the circle of the pile number red. Every time a pier column is poured, a red tick will be drawn at the "certain # pier" shown above the box

after the Spring Festival, project managers and labor workers returned to the construction site in time, quickly resumed work, quickly carried out labor competitions, and set off a construction boom. The construction of the project department in the spring of the year of the tiger has been greatly accelerated, and the "work potential" is rapid. Under the background that more than half of the pile foundation has been built in 2009, the "progress wall" of the project department can easily complete the tensile and compressive stress experiments

the closure of continuous beams across the north extension line of the first ring road in Foshan is just around the corner.

speed of resumption of work

speaking of the rapid resumption of work of project managers and labor workers, there is one thing that cannot be mentioned

one month before the Spring Festival in 2010, the project leaders started the deployment and arrangement of the construction site during the Spring Festival. The project leaders widely solicited the opinions of employees and labor workers on whether to carry out construction as usual or go home for the Spring Festival

in the face of the beautiful appeal of the employees to "let most people return home for the holiday and a small number of people stay at the construction site", after comprehensively considering the construction process in 2010, and bearing in mind the usual tradition of Chinese people's Spring Festival reunion, the project leader decided to have a spring festival holiday, and also put forward specific requirements for the project progress in 2010. The project personnel and labor workers made solemn commitments to ensure the construction schedule of the year of the tiger. Strengthen the special rectification of consumption blackmail, infringement of personal information, advance card running and other consumption pain points and blocking problems

the eighth day of the first month of 2010 is the resumption date of the project department, and the personnel of all roads are in place quickly. At the beginning of resumption of work, the project leaders decided to increase the input of manpower and equipment and take measures to optimize the allocation of human and material resources

after the short break of the Spring Festival, in order to fulfill the progress promise made before the new year, the bridge builders quickly entered the working state, and the first pile, the first cushion cap and the first pier in the year of the tiger were poured in the first week

the construction of two pile drivers at the 189 # pier of the continuous beam at the inner span and the road at the same time

the speed of the competition

the leaders of the project department make overall planning and give consideration, and firmly grasp the top priority of the construction of four continuous beams of the Baini River Bridge. According to on-site technicians, the first continuous beam across the north extension line of the first ring road in Foshan will be closed in late April this year

due to the relatively high technical difficulty and time-consuming of continuous beam construction, in order to better control the construction rhythm and ensure the construction period plan, the project leaders decided to put two pile drivers on the site at each pier of the continuous beam across Lihe Road, the continuous beam across Guihe road and the continuous beam across Liguan Road, which are still in the stage of pile foundation construction

as dozens of pile drivers were installed on the whole line almost at the same time, the construction site soon set off a wind of competition

the labor competition between two pile machines at one pier, between this pier and another pier, between this continuous beam and another continuous beam, and between the pile foundation of the continuous beam pier and the pile foundation of other piers will soon be staged. Everyone raced against time, catching up with each other, and gave full play to the spirit of labor competition

the speed with which the project personnel return to work is not just to fulfill their original commitments, because they also know that the rainy season in South China is coming, so we must cherish the good weather, rush for time and strive for progress

in addition, the requisition and demolition within the project bid section is coming to an end, and the easy solution of this big problem has greatly encouraged the project personnel. "The plan of the year lies in spring", which also strengthened their belief:

"there is no problem that can defeat the project builders." (correspondent xiaowenbin)